10/23/2017

Failed Project Series - The Aurora CO VA Administration Hospital

Failed Project Series

Construction project failures of bygone years often offer an educational perspective on the follies of project leaders and design professionals. Most of the time, the anecdotes act as horrible warnings, not excellent examples, of what (not) to do to complete a project on time and on budget.

However, when the failed project involves a federal government, hundreds of millions of dollars in cost overages, and is still in the making, the "lessons" are harder to watch. The facts of the Aurora CO Veteran’s Administration (VA) hospital case, however, continue to offer excellent lessons in what not to do when launching a project of any size or complexity.

Background on the Project

In 2007, the U.S. Veteran's Affairs Administration (the VA) began the design phase for a Veteran's Medical Center and Hospital University in the Denver suburb of Aurora. The goal was to create a state-of-the-art medical campus across 31 acres. Its original budget was $582.8 million with an estimated completion date sometime in 2014. In 2010, the VA signed on Kiewit-Turner (KT) as the general contractor, which promptly began pre-construction work.

Aurora-VA-plansA preview of what the 31 acre state-of-the-art medical campus was to look like.

Early Errors

Within months, KT determined that the budget was too low, and, to address the concern going forward, it and the VA created "The Book" - a guide to the construction plan that escalated the budget to $604 million. "The Book" also gave KT additional allowances from the initial agreement, as well as authority to make design changes. Unfortunately, official management of the project was vested in the VA's Washington D.C. office, not the local Colorado office, and those distant VA executives disagreed with the new terms.

Further, because there were no VA authorities on-site to review, well, anything, no one at the D.C. office bothered to look at "The Book." Eventually, one of the D.C. managers flew in from the Capital to "negotiate new terms," which resulted in a hand-written note of only 70 words that acted as the "contract" between the two entities. It stated KT would build the complex for $604 million and the VA would provide the design.

How can you avoid project failure? This ebook provides 8 best practices for  optimizing your resources. Click to download.

Failed Documentation

Not surprisingly, a multi-million dollar "contract" drafted on a single paper failed to provide the guidance and structure needed for such a mammoth project, but that wasn't what eventually cratered the project. In retrospect, according to the Army Corps of Engineers (ACE), the principal cause of the catastrophe was the VA's choice to move forward with the project using an "integrated design-construct" (IDC) contract model (which preceded the one-pager noted above).

With this method, the architect and contractor were expected to work together from the initial planning stages and throughout the building process, consulting and collaborating as the project matured. However, by the time KT joined in 2010, the architects had been at work designing the complex for three years, and disagreements between the two quickly stalled progress:

  • The initial contract with the VA designers did not specify construction costs, so they were left virtually unfettered to make changes as construction continued.
  • Often, consultations with medical professionals lead to design changes, although the health care personnel did not (or were not asked to) consider costs when making recommendations.
  • By 2012, more than 1,400 change orders had been requested by the VA designers, creating massive cost overruns and significantly delaying the completion of the project.

Asking for Help

In 2013, KT gave up trying to work with the VA and filed a lawsuit against it for breach of contract, stating that the designs it provided could not be completed within the $604 billion budget. Instead, by KT’s estimates, the cost of the project had soared to over $1 billion. The lawsuit stopped all work at the site, and in late 2014, when the Civilian Board of Contract Appeals ruled in KT's favor, the company elected to withdraw from the project altogether.

KT letterA letter from Kiewit-Turner to VA, courtesy of the Denver Post.

The Appeals Board had also noted that the VA neither had the funds to complete the project at that time nor did it have plans to ask for more money for that purpose. Congress then turned control of the project (and all VA projects over $100 million) over to the ACE.

Months later, in late 2015, the ACE concluded that the VA's contract-management (IDC) choice was the primary cause of the debacle and that completing it would take another two years and bring the total cost to $1.67 billion. ACE awarded the $571 billion completion contract to - Kiewit Turner, which picked up where it had left off two years earlier.

Updates on the Project:

  • In January 2017, the VA dodged a different kind of delay when the Trump administration agreed to lift its federal employee hiring freeze. The freeze would have prevented the hiring of 300 additional workers needed at that time to activate the center.
  • The former director of the VA's Office of Acquisition, Logistics, and Construction (now retired) said he had not been told the actual value of the cost overruns when he was removed from the project in March 2015.
  • No, the building project is not yet complete. In June 2017, the ACE projected it would be finished by mid-2018 at the cost of $1.7 billion.
  • Also in June, the VA asked Congress for another $1.4 billion to complete another 11 building projects stalled because of differences in VA and ACE contracting practices.

Lessons Learned

  1. Develop the contract to specify the activities and costs of each party involved in the project.
  2. Have the contract in place before starting work.
  3. Specify a procedure for making changes, then follow the procedure.
  4. Have (preferably local) management on site as often as possible.
  5. Presume project contracts of almost every type should be more than 70 words.

 

Card image cap

Failed Project Series

The Airbus A380 fiasco ended up costing over $6 billion. What can you learn from this failed project?

Topics: Failed Project Series

Subscribe to Our Blog

Recent Posts